Sudarshan HDPE PLB Ducts

Sudarshan HDPE PLB Ducts, manufactured as per TEC 2019 standards and certified by TSEC with RITES inspection, are designed to protect and secure fiber optic cables in various critical infrastructure projects. These ducts feature a permanently lubricated inner layer that minimizes friction, ensuring smooth installation and reducing the risk of cable damage. Ideal for underground laying of optical fiber cables, Sudarshan PLB Ducts are extensively used in Indian Railways for telecom and signaling, 4G/5G network deployments, the prestigious BHARATNET project, and more. Whether for telecommunication, metro systems, or national highways, these ducts offer superior protection and durability.

Technical Specifications

SUDARSHAN PLB HDPE DUCT PIPES
AS PER TECH - 2019 (TEC/ GR/ FA/ CDS-008-04/AUG-19)
SL NO
NOMINAL DIA
WT MAX. MIN
INNER LAYER
WALL THICKNESS
WT/MTR
OD MIN
OD MAX
SIZE
WT
WT+-
WT – MIN
WT – MAX
WT- MIN
WT - MAX
1
32MM
32.3
32/26
3
0.2
0.24
0.36
2.8
3.2
0.262
2
40 MM
40.4
40/33
3.5
0.2
0.28
0.42
3.3
3.7
3.385
3
50 MM
50.5
50/42
4
0.3
0.32
0.48
3.7
4.3
0.555
4
63 MM
63.6
63/57
3
0.4
0.36
0.54
2.6
3.4
0.543
5
63 MM
63.6
63/57
3
0.4
0.36
0.54
6.1
6.9
1.108
6
75 MM
75.7
75/76
5
0.5
0.4
0.6
4.5
5.5
1.055
7
90 MM
90.9
90/79
5.5
0.5
0.44
0.66
5
6
1.402
8
110 MM
111
110/96
7
0.6
0.54
0.84
6.4
7.6
2.173
9
110 MM
111
110/80
15
06
0.54
0.84
14.4
15.6
4.298

PERFORMANCE Requirement (ACCEPTANCE TEST)

1
Internal Pressure Creep Rupture Test of Pipe (Acceptance test) Duration-48h Temp-80°C
Visual
Cl-8.1.1, Of IS-4984:2016 & Table-5 Of- TEC/GR/FA/CDS-008/04/AUG-19
Table-5 Of- TEC/GR/FA/CDS-008/04/AUG-19
The Pipe under test shall not show signs of localized swelling, leakage o weeping and shall not burst when tested at Test Temperature a 80° C for 48 Hours, Induced Stress as per Table 5 of TEC/GR/FA/CDS-008/04/AUG-19
2
Internal Pressure Creep Rupture Test of Pipe joint (Acceptance test) Duration-165h Temp-80°C
Visual
Cl-8.1.1, Of IS-4984:2016 & Table-5 Of- TEC/GR/FA/CDS-008/04/AUG-19
Table-5 Of- TEC/GR/FA/CDS-008/04/AUG- 19
The Pipe under test shall not show signs of localized swelling, leakage o weeping and shall not burst when tested at Test Temperature a 80° C for 48 Hours, Induced Stress as per Table 5 of TEC/GR/FA/CDS-008/04/AUG-19
3
Reversion
Measured by Hot Air Oven.
8.2, Annex F of IS:4984 - 2016
Cl-4.6 TEC/GR/FA/CDS-008/04/AUG-19
As per CI. No.8.2 , Annex F of IS:4984 – 2016 & Cl-4.6,TEC/GR/FA/CDS-008/04/AUG-19 the Longitudinal reversion shall not be greater than 3%
4
Melt Flow Rate
Measurement by MFI Tester
Cl-4.19
TEC/GR/FA/CDS-008/04/AUG-19 & IS-2530:1963
When tested from a composite sample of Min three pipes as per IS 2530 at 190° C with nominal Load of 5 Kgf MFR shall not deviate from the MFR of the resin by more than 30%
5
Oxidation induction Time
Measured By OIT Tester
Cl-4.13 & Annex-1
TEC/GR/FA/CDS-008/04/AUG-19
The minimum Oxidation Induction Time of the pipe when tested in accordance with the method given Annex 1 , shall be not less than 30 Minutes.
6
Density
Measurement by Density Tester
Cl-4.18
TEC/GR/FA/CDS-008/04/AUG-19
when tested from a composite sample of Min three pipes as IS 7328 the Base Density of pipe shall be between940 to 958 Kg/m3.
7
Tensile Strength & Elongation
Measurement by UTM Tester
Cl-4.5
EC/GR/FA/CDS-008/04/AUG-19
Test according ASTM F2160 & ASTM D638 the test specimens Punch / Machined from pipe samples, the Elongation shall be ≥ 500.% & Tensile strength at Yield- ≥20N/mm².
8
Environment stress crack Resistance
Measured by ESCR Tester
Cl-4.7
EC/GR/FA/CDS-008/04/AUG-19
Test according to ASTM D-1693, There shall be no failure/crack.
9
Impact strength
Conducted by Impact Testing machine
Cl-4.8
EC/GR/FA/CDS-008/04/AUG-19
Test according to IS-12235 Pt-9, the Duct shall not crack or split.
10
Crush Resistant
Conducted by Crush resistant Tester
Cl-4.9
EC/GR/FA/CDS-008/04/AUG-19
The deflection with load on and after recovery period(5min) shall not exceed 10% & 2% Respectively
11
Mandrel Test
Visual
Cl-4.10
EC/GR/FA/CDS-008/04/AUG-19
150mm long mandrel of dia 3mm less than the internal dia of duct shall be passed through a 5meter length of Duct freely throughout the length, when the duct is bent to a radius of 5Meter
12
Internal Co-Efficient of Friction
Measurement by UTM Tester
Cl-4.15 & Annex-2
EC/GR/FA/CDS-008/04/AUG-19
a) For Nylon Jacketed unarmored OFC : 0.06 Max. For HDPE PLB Ducts
b) For HDPE Jacketed Unarmored OFC: 0.20 Max. For HDPE PLB Ducts
13
Ash Content
Conducted by muffle furnace
Cl-4.2
EC/GR/FA/CDS-008/04/AUG-19
The ash content of the duct shall not be more than 0.3%
14
Test for fading of colour of duct
Visual
Cl-4.21
EC/GR/FA/CDS-008/04/AUG-19
When Tested Accordance to ASTM D-1712,There shall be no Discolouration
15
Pulling force required to pull out two pieces of Duct Joint by Coupler
Visual
Cl-5.2
EC/GR/FA/CDS-008/04/AUG-19
The test may be conducted by loading the coupler joined by two pieces of duct for 15 minutes using UTM Pulling force required: - 110/80-800kgf
63/50-550kgf
50/42-450kgf
40/33-320kgf
26-250kgf

Download the brochure for more information about Sudarshan pipes and fittings.